Government of Azad Jammu & Kashmir

Net Metering Application and Technical Requirements

Consumers planning a rooftop solar or other eligible renewable-energy system should understand the AJKED approval process before connecting the system to the electricity network. Net metering is a regulated interconnection arrangement, not simply the installation of panels. It requires an eligible consumer connection, approved equipment, suitable protection and an authorised metering setup.

Regulations and procedures

The department’s published information refers to the AJ&K Distributed Generation (Alternative & Renewable Energy) and Net Metering Regulations, 2022. It also records that standard operating procedures were prepared and vendor, installer and service-provider registration was started. Regulations and procedures can be revised, so applicants should request the latest version from AJKED before preparing a system design.

Eligibility and network review

Eligibility may depend on the consumer’s connection status, sanctioned load, proposed system capacity, location, applicable regulations and technical condition of the local network. Contact the relevant electricity office to confirm whether the connection can be considered and what documents are required.

System design and installer selection

Ask a qualified solar professional to prepare a design that identifies the proposed capacity, inverter specifications, protection equipment, isolation arrangements and metering requirements. Verify the installer’s current registration or authorisation with AJKED. A firm appearing in an older vendor list is not guaranteed to remain registered today.

Application and technical assessment

The department may request an application, consumer documents, system drawings, equipment specifications and other technical information. The proposed interconnection may be reviewed and inspected. Consumers should wait for written approval and the authorised metering arrangement before operating the system in parallel with the distribution network.

Joint ventures and registration conditions

An earlier AJKED vendor-registration notice stated that joint-venture applications would not be considered under that registration process. Because vendor registration conditions may be revised, confirm the latest instructions before preparing or submitting an application.

Safety, billing and consumer records

Keep the approved design, equipment documents, inspection record and interconnection agreement. Billing treatment for imported and exported energy depends on the rules and agreement applicable to the connection. Do not rely on online estimates or old promotional material to calculate financial returns. Ask AJKED for the current written rules before purchasing equipment or signing a contract.